• North America, Canada
  • 46 MW Onshore Wind
  • Delivered into Operation
  • Developed and Constructed by:

    Mainstream Renewable Power

  • Operated by:

    APEX Clean Energy

  • Technology Supplier:

    Siemens (20 x2.3MW)

  • Sold to:

    IKEA Group

  • Commercial Operation Date:

    Quarter 3, 2014

Overview

The Oldman 2 wind farm is located in Alberta, Canada.  The wind farm is Mainstream’s first project in Canada.  Construction started on the wind farm on 23 September 2013 and it reached commercial operation date on 5 September 2014.  At the point of generating electricity, giant furniture retailer, IKEA purchased the plant.   APEX Clean Energy are operating Oldman 2.

The wind farm has a capacity factor of 40.9% and some 107,120,000 kg of Co2 is avoided each year.  